BULLETIN ON CAPITAL CONSTRUCTION LAW

REGULATIONS ON TIME FOR POSTING THE CONTRACTOR SELECTION PLAN

ON THE NATIONAL BIDDING SYSTEM

AND TIME FOR CONTRACTOR SELECTION

According to the statistics of the National Bidding Network System (http://muasamcong.mpi.gov.vn), from March 15, 2019 to March 17, 2019, there were 137 notices of delayed contractor selection plan. compared to the time specified.

So what is the time for posting information and performing other jobs in the process of selecting contractors?

Bidding Law and Decree No. 63/2014 / ND-CP dated June 26, 2014 of the Government:

I. Time for posting information on bidding network and issuing bidding documents:

 Stipulated in Clause 1, Article 8 of Decree 63/2014 / ND-CP

1. Information on contractor and investor selection plans; Short list; Results of contractor and investor selection: Information must be posted no later than 07 working days from the date the document is issued.

2. Time limit for commencement of issuance of EOI request, prequalification invitation, bid invitation dossier, request dossier: At least 03 working days from the first day of posting the notice of invitation for submission interest, notice of prequalification, notice of bid invitation, notice of invitation for sale are posted on the national bidding network system.

II. Time to perform other jobs in the contractor selection process:

Provisions in Clause 1, Article 12 of the Bidding Law

1. The time limit for approving a contractor selection plan is 5 working days after receiving an appraisal report;

2. The time limit for preparing a dossier is at least 5 working days, counting from the first day the request dossier is issued to the date of bid closure. Contractors must submit dossiers of proposals before time of bid closure;

3. The minimum time for bid preparation is 20 days for domestic bidding and 40 days for international bidding, counting from the first day the bidding dossier is issued to the date of bid closure. . Contractors must submit bids before the time of bid closure;

4. The maximum time for evaluation of a proposal is 30 days, for a maximum of 45 days for domestic bidding, from the date of bid closure to the date the bid solicitor submits to the investor for approval. approval of contractor selection results. In case of necessity, the time may be extended but for not more than 20 days and the project implementation schedule must be ensured;

5. Maximum appraisal time is 20 days for each evaluation content: contractor selection plan, invitation for expression of interest, prequalification documents, bidding documents, request for proposals, results of selection Select a contractor from the date of receiving a complete submission dossier;

6. The time limit for approving an expression of interest, invitation for prequalification, request for proposals, or tender invitation documents is 10 days at most from the date of receipt of the written request for approval of the expression of interest. prequalification documents, bid invitation dossiers, dossier of requirements of the bid solicitor or evaluation report in case of appraisal request;

7. The time limit for approving or handling comments on the contractor selection results is 10 days at most, counting from the date of receipt of bid solicitors' written requests for approval of contractors or evaluation reports. determination in case of evaluation request;

05/04/2019 Views: 24.491
* TIÊU ĐIỂM
[ * ] RELATED ARTICLES
In the Q and a fiscal policy on the official website of the Ministry of Finance on 08/06/2020, the Ministry of Finance has responded to the questions of readers relating to Circular No. 10/2020/TT-BTC dated 20/02/2020 regulations on the settlement of the project to complete use of state capital. We quote below for your reference.
During the review of the online tender tender (E-HSDT), the invite party requires the contractor to provide the original for the collation, clarifying the tender record. Is this true to the provisions of applicable law? What is the legal basis of this regulation?
the Ministry of Finance responded to readers' questions about the transitional handling issue of Circular No. 10/2020 / TT-BTC dated 20/02/2020 provides for the settlement of completed projects using State capital. We would like to quote below for your reference.
In the Financial Policy Questions and Answers section on the Ministry of Finance's official websites on March 26, 2020 and April 16, 2020, the Ministry of Finance responded to readers' questions and clarified some contents. Regarding Circular No. 10/2020 / TT-BTC of February 20, 2020, providing for settlement of completed projects funded with state capital.
On January 20, 2020, the Government issued Decree No. 11/2020 / ND-CP providing regulations on administrative procedures in the field of State Treasury. This Decree takes effect from March 16, 2020.
[ * ] ARTICLES SEARCHING FOR AUTOMATION
ECOVIS AFA VIETNAM AUDITING - APRAISAL AND CONSULTING CO., LTD
Address: 142, Xo Viet Nghe Tinh Street, Hoa Cuong Nam Ward, Hai Chau District, Da Nang City, Viet Nam
Tel: +84.236.363.3333 Ext: 201 - Email: info@ecovis.com.vn
Website: http://www.afac.com.vn; Web: https://www.ecovis.com/vietnam/audit
0
afac.com.vn; kiểm toán; audit; kế toán; thuế; Thẩm định giá; afaafac.com.vn; kiểm toán; audit; kế toán; thuế; Thẩm định giá; afaafac.com.vn; kiểm toán; audit; kế toán; thuế; Thẩm định giá; afaafac.com.vn; kiểm toán; audit; kế toán; thuế; afa; Thẩm định giáDesign by: 24hdanang + 0905512238 + MAI ĐỨC TUẤN + 0905512238
Tiếng Việt